Hi;
I'm working on resource planning for our projects right now and wonder if there is a way of planning based on working hours or based on periods of 1/4 days (not only based on work days)? Or if not; do you have plans for implementing such functionality?
Check out and follow this post which talks about this functionality. We are releasing an update next week that will give users the ability to set durations in hours, minutes, etc and will update that post when more information is available.
https://community.smartsheet.com/discussion/need-column-property-type-clock-or-time-day
I am happy to announce the ability to set partial day duration (hours, minutes, and seconds) is here! Check out my announcement for more information and to ask questions: https://community.smartsheet.com/announcement/new-smartsheet-critical-path-and-duration-minutes-hours-and-weeks