Project Tracking that includes working day tasks and calendar day tasks
Hi All,
I am attempting to manage a project that includes tracking tasks that follow our company's cultivation process in addition to production tasks. As most of us know, plants don't take the weekend off... Has anyone found a good workaround in project settings to account for this kind of project tracking variability? We see a ton of issues when we try to override the settings in either direction. I want to make this as simple as possible for my team, but so far I am stumped.
Best Answer
-
Turns out I was able to answer my own question. For anyone having a similar question the answer is "elapsed time". The following excerpt explains how it gets around project settings for working days in a project.
- "Elapsed time (lead with an e to indicate duration in elapsed time e.g. e3d, e5h, e3.5d, etc). A task with a duration in elapsed time ignores non-working time. The task will start and end in the amount of time specified regardless of working day length and non-working days in the sheet."
To read the full article go HERE.
Answers
-
Turns out I was able to answer my own question. For anyone having a similar question the answer is "elapsed time". The following excerpt explains how it gets around project settings for working days in a project.
- "Elapsed time (lead with an e to indicate duration in elapsed time e.g. e3d, e5h, e3.5d, etc). A task with a duration in elapsed time ignores non-working time. The task will start and end in the amount of time specified regardless of working day length and non-working days in the sheet."
To read the full article go HERE.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives