Use Predecessors for a Shared Start Date and Extended End Date
I am working on a marketing project plan template, and some of our campaigns spend multiple days in market. Tracking the performance of these projects happens for the duration of the project plus the duration of an attribution window.
Example: An email campaign launches on 4/1 and runs through 4/7, and any email leads generated 4/1 through 4/21 are counted towards the email campaign (7-day campaign + 14-day tracking window).
If I have a row for "In-Market Date" and a row for "Collect Performance Data", is it possible to use predecessors to sync this activity? So that they always share the same start date, but 'collect performance' always ends two weeks after 'in-market date'?
Thanks!
Answers
-
Hi @cbrucher
You can use a SS (start-to-start) dependency type to make sure the "Collect Performance Data" starts on the same date. See the bottom of this article: Work with Duration and Predecessors
Then in regards to ending 2 weeks after, you'll just need to ensure the Duration for that second task is 14 days more.
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 412 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 140 Just for fun
- 57 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives