Utilization Tool
Bruce Southers
✭✭✭
Hello All,
Has anyone created a tool for tracking PM hours worked on projects, that can go to a backend sheet and thus create a utilization number per PM? I have myself and another person on our team, and want to show active projects and then be able to track hours worked weekly on those projects. Ideally using a form to input the data, but if not feasible, that would work too.
Thanks for any ideas.
Bruce Southers
Sr. Project Manager
Frost Brown Todd LLC
Tags:
Answers
-
Hi Bruce,
Yes, we've done this and it works well! We created a solution for a customer that looks like this:
- Hours sheet with a form that includes a project select dropdown (This dropdown is easy to maintain if you have Data Shuttle)
- Project List including formulas that pull hours worked for each project from Hours sheet
- Metrics Sheets with formulas to reference Hours sheet and calculate desired metrics
I hope this helps. Feel free to reach out if you have questions.
Julie Fortney
julie.fortney@swc.net
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives