Can I automatically adjust predecessor dates by changing the dependent date?

Options

I'm looking to create a dynamic project schedule with the functionality described below and would appreciate any help from the Community!

Our dependent task end date changes rather frequently based on shifting priorities. I would like to change the final dependent end date (in this example, 'swim') to 3 days later (9/10) with the same duration, and have all of the predecessor task start & end dates change to 3 days later as well.

When I try to change the start date of the dependent task to 3 days later, I get the below error message.

When I try to change the end date of the dependent task to 3 days later, it just changes the Duration of the dependent task.

Any help is super appreciated - thanks!

Answers

  • Sameer Karkhanis
    Sameer Karkhanis ✭✭✭✭✭✭
    Options

    You should change the dates of the predecessor and not the task that it dependent on it. In your case change the date of "walk to pool" from 9/5/22 to 9/8/22 and rest will be automatically adjusted.