Can I automatically adjust predecessor dates by changing the dependent date?
I'm looking to create a dynamic project schedule with the functionality described below and would appreciate any help from the Community!
Our dependent task end date changes rather frequently based on shifting priorities. I would like to change the final dependent end date (in this example, 'swim') to 3 days later (9/10) with the same duration, and have all of the predecessor task start & end dates change to 3 days later as well.
When I try to change the start date of the dependent task to 3 days later, I get the below error message.
When I try to change the end date of the dependent task to 3 days later, it just changes the Duration of the dependent task.
Any help is super appreciated - thanks!
Answers
-
You should change the dates of the predecessor and not the task that it dependent on it. In your case change the date of "walk to pool" from 9/5/22 to 9/8/22 and rest will be automatically adjusted.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives