Can I automatically adjust predecessor dates by changing the dependent date?
I'm looking to create a dynamic project schedule with the functionality described below and would appreciate any help from the Community!
Our dependent task end date changes rather frequently based on shifting priorities. I would like to change the final dependent end date (in this example, 'swim') to 3 days later (9/10) with the same duration, and have all of the predecessor task start & end dates change to 3 days later as well.
When I try to change the start date of the dependent task to 3 days later, I get the below error message.
When I try to change the end date of the dependent task to 3 days later, it just changes the Duration of the dependent task.
Any help is super appreciated - thanks!
Answers
-
You should change the dates of the predecessor and not the task that it dependent on it. In your case change the date of "walk to pool" from 9/5/22 to 9/8/22 and rest will be automatically adjusted.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.1K Get Help
- 444 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 5K Ideas & Feature Requests
- 83 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 35 Webinars
- 7.3K Forum Archives