Hi,
I have a building a PMO using Sciforma in the past and my new Company has selcted Smartsheet.
I am missing a tool to update the tasks of a project like I was having in Sciforma.
Tasks were organized in different categories :
- Fixed duration:
- if the task was not declared as "started", a project update was shifting the start date to the current day if the start date was in the past,
- otherwise, no changes
- Effort driven but fixed end date:
- if the task was not declared as "started", a project update was shifting the start date to the current day if the start date was in the past
- otherwise, the saturation was calculated by using total workload, hours already spent and remaining time
- Effort driven floating end date:
- otherwise, the saturation was calculted by using total workload, hours already spent and remaining time
- if the task was not declared as "started", a project update was shifting the start date to the current day if the start date was in the past
- otherwise, the end date was calculated by using total workload, hours already spent and saturation
Are you considering developping such functionalities ?