Automatic Update of a project

Options

Hi,

I have a building a PMO using Sciforma in the past and my new Company has selcted Smartsheet.

I am missing a tool to update the tasks of a project like I was having in Sciforma.

Tasks were organized in different categories :

  • Fixed duration:
  • if the task was not declared as "started", a project update was shifting the start date to the current day if the start date was in the past,
  • otherwise, no changes


  • Effort driven but fixed end date:
  • if the task was not declared as "started", a project update was shifting the start date to the current day if the start date was in the past
  • otherwise, the saturation was calculated by using total workload, hours already spent and remaining time


  • Effort driven floating end date:
  • otherwise, the saturation was calculted by using total workload, hours already spent and remaining time
  • if the task was not declared as "started", a project update was shifting the start date to the current day if the start date was in the past
  • otherwise, the end date was calculated by using total workload, hours already spent and saturation

Are you considering developping such functionalities ?