Individual Resource Calendars Built in Project Schedules
As a PM I would Like to Create PTO Calendars for my Resources or Project Calendar, so that it will Not Schedule work on those Days for those Resources. Today I have Manually Look at there PTO Calendars (External App) and Adjust My Project Schedule. This is Time Consuming and inefficient.
Thanks
Comments
-
YES! I agree with this. Voted up!
-
The last update to this question was 12/12/22! This is 02/21/2024! Have you all forgot about this?
-
I agree with this as well. My projects use resources in North America & Asia which have different work weeks & holidays. I need the ability to create/assign different resource calendars within a Project schedule.
-
Is there any progress or plan to have SS support individual resource calendars? Seems like a major basic feature
-
This has been my frustration ever since I started using SS. I came from MS Project and could assign a different calendar to a task. I just don't see how this is not a basic function in SS given that lots of companies are global.ποΈ