I want changes to the start/end dates in Smartsheet to update/sync in Resource Mgmt
Sign in to see the current vote count, add your own vote, or leave a comment.
Hi @Becky M.
Can you clarify your specific scenario and when your dates are not updating?
Currently, if you have linked the project plan in Smartsheet with Resource Management, then task changes (such as start/end date changes) can flow between the two products. In Smartsheet, you will need to use the Resource Management Panel and click "Update" to push your changes to Resource Management.
Cheers,
Genevieve
The start and end dates of the project do not update as shown below. Perhaps I am misunderstanding what the dates below the project name represent, but it seems like it should be the start/finish dates of the whole project.
I noticed this the other day and tested Ctrl + M – it does not work. I submit ticket to Smartsheet support – they told me that’s expected behavior because it’s not currently available even though it still shows as keyboard shortcut in the menu🙄 and told me to submit new product idea. Please add this keyboard shortcut to…
Summary of Issue All team members work a standard 7.5‑hour day, but only a portion of that day is allocated for project work (e.g., 25%, 50%, etc.). In Resource Management, however, the system currently interprets allocations as a percentage of the full 7.5 hours, instead of the project‑eligible portion of a person’s day.…
Dashboard widgets are currently mostly static. I can display counts and charts, but I cannot click into a specific part of a widget to drill into the underlying records. It would be a big usability improvement if widgets supported interactive drill-down. For example: Click a bar segment (or stacked segment) to open the…