I have a question about the percentage during the project, because my% predicted on the date and my% Complete, does not hit when they are the same.
I think your formula aide is hiding part of the answer.
There are a couple of different factors at play here.
1. [% Complete] children are entered manually. Unless your manual entries match the predicted, they will diverge.
2. If you check rows that are supposed to finish today, since you use greater than instead of greater than or equal to, you may get odd results because the End Date for today is (probably) at the end of the work day, which may or may not line up with the value returned by TODAY()
3. [% Complete] roll up is based on the sum of the individual durations and your prediction is based on the start and end dates. If there are any gaps or overlaps, the two numbers will diverge.
There's more, but should get you started.
Craig
Hello, I'm working through the writing formulas optional activity and in the 'Nested IF function - Progress Column' task it directs you to put in the following formula '=IF([% Complete]@row = 0, “Empty”)'. However, when I put this formula into the spreadsheet, '04a_Marketing Request Tracker - Formulas', I get an…
Currently Triggering recurring workflows are only supported at the top of each hour. For instance 10:00, or 11:00, etc. Would like the ability to set 10:30 or 10:45. Perhaps the inteface can stay hourly so it doesnt get huge, but have the ability to manually edit the time directly to any custom time.
I have an automation that has a condition where I am looking at the column "LEA Interco Supporting Site(s)" and trying to find columns that have the value "Fort Loramie" in them. This works well when "Fort Loramie" is the first item listed in the cell, but it doesn't work when "Fort Loramie" is the second or third value in…