Hi,
I need help with finding a way to automate the RYG balls so that if no dates are input, it's white. If the first date is input, it's red. If the second date is input, its yellow. And if the final date is input, it's green.
Thank you !
Try something like this.
=IF(AND(ISBLANK([Welcome Email]@row); ISBLANK(Signed@row); ISBLANK(Cosigned@row)); ""; IF(ISDATE(Cosigned@row); "Green"; IF(ISDATE(Signed@row); "Yellow"; IF(ISDATE([Welcome Email]@row); "Red"))))
The same version but with the below changes for your and others convenience.
=IF(AND(ISBLANK([Welcome Email]@row), ISBLANK(Signed@row), ISBLANK(Cosigned@row)), "", IF(ISDATE(Cosigned@row), "Green", IF(ISDATE(Signed@row), "Yellow", IF(ISDATE([Welcome Email]@row), "Red"))))
Depending on your country you’ll need to exchange the comma to a period and the semi-colon to a comma.
Did it work?
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Wow! It works perfectly!
Many thanks
Excellent!
Happy to help!
I'm sorry to have another question, perhaps you can advise me why when I changed the order and updated the form's names, the ball doesn't change to green when the welcome email date is present?
You can see in the photo, the blank, gray and yellow work, but not green.
=IF(AND(ISBLANK([Welcome Email]@row), ISBLANK([TPSA Signed]@row), ISBLANK([Counter Signed]@row)), "", IF(ISDATE([Counter Signed]@row), "Yellow", IF(ISDATE([TPSA Signed]@row), "Gray", IF(ISDATE([Welcome Email]@row), "Green"))))
I changed it to RGYG
Thank you
It is the order in which you have your conditions. Once it comes across it's first true value, it stops evaluating. So if yellow and green are both true, but yellow comes first, it will trigger a yellow response, but if green comes first in your formula, it will trigger a green response. Try working your formula in order of priority...
=IF(ISDATE([Welcome Email]@row), "Green", IF(ISDATE([Counter Signed]@row), "Yellow", IF(ISDATE([TPSA Signed]@row), "Gray", "")))
I saw that Paul answered already!
Let me know if I can help with anything else!
Andrée
How can I delete old sheets I no longer use from my account?
I'm trying to display a task progress chart showing "complete", "late", and "not complete" in my dashboard and for some reason the chart will display as a column chart but it won't display as a donut chart even though I'm referencing the same report. I'd prefer to display as a donut chart as I think it looks better and is…
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…