Hi I am attempting to move our production schedule from MS Project to Smartsheet. But I am having difficulty with showing the start times and finish times per task and have it auto-update based on the hours manually entered into the sheet..
The duration column reads days only, and the sheet only shows start date and finish date based on this column. I would also like it to show the start time of the job, say 6am, if duration is 3 hours then finish time is 9am, and so on.
see below snapshot of my smartheet as it is, with a snapshot of our MSProject schedule