@Kaleb here it is: https://app.smartsheet.com/sheets/vX8g5HXPjj22Mq9VGfHXWCFXrHRhr4wcmQw47971
For the:
- New Baseline: with the formula =End@row
I actually changed it to manually add the data manually as soon as the new task is added, otherwise, it will keep updating everytime I change the end date.
In this example, activities 5 & 6 have been added after setting the baseline. Original end date was 09/25 (as stated in New Baseline column) and then I changed it to 09/27. After that, "Diff" column is either picking up the original Variance from the Var column or calculating whenever it is blank.