Why dont non working days carry thru to other projects?
I ticked the box to apply to all of account but they dont show or take effect in other projects?
What am I missing or did not do?
Best Answer
-
If you've set working days for your organization at the account level, this will only apply to newly created sheets moving forward, unless they were created through a Template. Sheets from a template will inherit the Template settings.
Here's more information: Working days, non-working days, and holidays at the account level
Cheers,
Genevieve
Answers
-
If you've set working days for your organization at the account level, this will only apply to newly created sheets moving forward, unless they were created through a Template. Sheets from a template will inherit the Template settings.
Here's more information: Working days, non-working days, and holidays at the account level
Cheers,
Genevieve
-
Thanks G