Elapsed Days in Predecessor Field

2»

Comments

  • Please add this feature! It would be incredibly helpful!

  • ✭✭

    +1 for this feature request, very important feature.

  • ✭✭✭✭

    Extremely important feature! There are many threads with this topic, but this seems most recent so hoping I can bump it here.

    My constant headache is that I manage many tech projects with weekend migrations - but migrations always have go/no-go dependencies, so I want to keep my predecessors in place in case anything shifts upstream.

    If a row has no dependencies, using elapsed time to override non-working days works just fine. But if the row has a predecessor, it's impossible to force the START date to begin on a non-working day.

    PLEASE FIX THIS!!

  • ✭✭

    In the Community discussions I see 4 years of comments on multiple threads asking to add the use of elapsed time in predecessors - why hasn't this been implemented yet? Even when both the predecessor & the active task both have a elapsed time Duration, it still calculates the lag time in working days. So frustrating when my project is based on dependencies between different groups that have different working hours.