Hi Everyone,
Do you know if it is possible to assign the same task to many users ? or a group of user ?
Thanks
Olivier
Hi Olivier,
Yes, it is!
You can use multiple contact columns to assign to different roles. Such as Project Manager, Consultant and so on.
Will that work for you?
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant / Get Done
Hi Oliver,
Yes it is a limitation, to assign the same task to multiple resources. No idea when this will be made available.
The workaround is that you need to have the same task twice in the plan and then assign task to the respective resource. This only "bloats" the plan, but i see this is the only way, especially if you are also looking at resource loading across projects.
Hope this helps..
Robert
As Robert and Andree mentioned, there are a couple of common approaches to this:
You can't currently add multiple people in the same cell, and this is something we're working on. There should be an update on this later this year.
Best regards,
Daniel
Hi everyone,
Thank you for your answers ;-)
I will follow your recommendation.
BR
Happy to help!
Andrée
Hi again Olivier,
Yes, assigning multiple people to a task is now available.
Please see the attached link/screenshot for more information.
https://help.smartsheet.com/articles/518335-assigning-people-to-a-task
Andrée Starå
Workflow Consultant @ Get Done Consulting
--
Hi all,
We're pleased to announce that you can now quickly & easily assign tasks to multiple people. To do so, check the new "Allow multiple contacts per cell" checkbox in any contact column. The cells in that column will then allow up to 20 people to be added.
You can still leave that option unchecked when you only want a single person to be assigned to a task at a time.
Adding multiple contacts to a cell is useful not only for assigning people, but also for other scenarios where you want to associate multiple stakeholders with a row. For example, you might want those people to receive notifications when the row changes, or you may want them to appear in reports and filters.
For some projects, you may want to add 2 contact columns: one for the primary owner, and another for additional team members.
We welcome you to try it out and let us know what you think.
- Daniel
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…
Hello team! Hope you all are having a wonderful holiday season. I am trying to set up an automation that will send an email reminder one time when Next Update Date = 60 days, then another automation at 30d, etc. The key is I only want it to send the reminder one time when Next Update threshold is reached. Is this possible?…
Has anyone found a workaround for sharing Smartsheet reports externally without giving access to internal data? I currently have to download the data and transfer it onto excel to create a pivot table for our client and I want to find an easier way to do so. I also already create a dashboard for our client, but I wanted…