-
Timeline View - Enhance Space for Milestone/Task naming
Dear Community-Members & Smartsheet Development Team, The long-awaited Timeline View feature was recently released. It is a very good feature to use for visual data sharing of timelines (ex. screenshots for presentations). However, we quickly realized in project management that a large number of names are cut off in terms…
-
Zeitachse
Welche gravierenden Vorteile hat die neue Darstellung "Zeitachse" gegenüber der bisherigen Gantt-Ansicht? Ist dies vorrangig eine andere Art der Visualisierung oder gibt es spezielle Funktionen, welche einzig über diese Darstellung ermöglicht werden? Welche Probleme löst diese neue Darstellungsmöglichkeit? Hat jemand…
-
Why don't I see the critical path?
Hello Community, I have predecessors and dependencies, but I don't really see a critical, summary or driving path even though I have clicked to show them. Can anyone tell me why? Thanks, Ashley
-
Gantt View Duration Zoom Levels
Now that we can add sub-second durations, please allow a zoom level that can view such durations. I need to visualize processes that are on the order of milliseconds.
-
Adjusting a Gantt view time for half day
Good afternoon, Is it possible through either setting a specific duration or formula to begin a task in the afternoon of a Monday and end at the end of day on Tuesday? I am creating a high-level view of an upcoming store project where some tasks beginning in the PM and finish the following AM and other tasks that start in…
-
Bookend a scheduler task with two predecessors & variable number of days
My smartsheet scheduler task will float between two predecessors… meaning it will start at the same time as one task (i.e. 10SS) and finish in coordination with another predecessor (i.e. 12FF). The number of days will technically be variable and change as the predecessors change. Smartsheet does not seem to allow this, but…
-
Merged: Gantt View: show milestones in the parent summary when collapsed
This discussion has been merged.
-
Starting with a Sheet, that Now needs to be a Gantt - how does one get roll-up summary info
We started with what we thought was going to be a simple sheet that has grown and now had Target Start and Target End date columns. Now we look at is as a Gantt (again not started as a Gantt sheet) So we made parent and child rows, have the settings in Gantt view looking at these date columns. However, if you indent/make a…
-
Critical path viewed when linked to a parent row
It would be nice to have the critical path show when linked to a parent row. I have a parent row (e.g. Testing) where the children (e.g. test 1, test 2, test 3,...) are performed in parallel & have the same finish date, so I often link the successor task(s) to the one parent row vs. each individual test task rows (can be…
-
Parent Row Color Settings: Task Bar in Gantt View
Is it possible to add the ability to change the parent row color settings, especially as relates to task bar color in gantt view?