Gantt view dates don't show correctly . . .
The dates shown in the Gantt view bars do not show line up with the actual dates stated in the Start Date and Finish Date columns - it is out of line by about 6 months. In the attached screen shot, for the overall project the Finish Date is 26/02/2021, but the Gantt bar shows the finish to be in middle of Q4 2021. It is…
-
Why is Gantt view not working for all items in a report?
I have a report that pulls from three different sheets. It uses Gantt view so I can track the status of projects I'm working on that come from three different areas. Gantt view shows just fine for all data pulled from two sheets, but not data pulled from the third. I'm not sure why. Please help.
-
How to set start date independent of predecessors?
Hi Community, I'm trying to figure out how to set a task start date without wiping out the predecessors but I can't figure out how? I've seen other posts with slightly different queries where people would simply suggest adding lag times or something similar so here's some additional info to show why that wouldn't work for…
-
Change "end date" based on status changes
When an end date is used in a dependency setting, you can't use automation or formulas to change it. However, this is when it is critical (pun fully intended)! When someone marks an item as Completed status, it would be helpful if the sheet could update the End Date column to the date it marked completed. For dependencies…
-
Simplified Visual Portfolio View
Hello, I am currently using the Project Management Office Template. I have many many projects in here. I am having trouble visualizing the Gannt charts when trying to pull in a lot of projects and compare. I'd like to get something very simple like this: I need to be able to see: How many projects I need to close per month…
-
Copy&Paste with relative predecessors
Hi, I have a schedule (created from Project template (aka Gantt chart)) where I have a section which is repeating several times in the schedule. Inside of a section I have dependencies linked using Predecessor field which do not point outside of the section itself. You can imagine this as an agile sprint schedule where…
-
Duration vs predecessors, for parallel activities (not auto updating on gantt chart)
based in the example below, I have various assignment and activities that run parallel to various construction activities across construction stage. How do i set smart sheet to prioritise predecessor? Research: this behaviour is a known limitation in Smartsheet. Unlike MS Project or Primavera, Smartsheet does not…
-
Gannt chart showing additional days when weekend working
When project settings include for working weekends, why when you give a task a two day duration starting on a Saturday, does it show it spanning 3 days (Sat, Sun, Mon) ? Is there a fix for this please ?
-
Add today line to Gantt Report in Dashboards
The today line should be visible when a report is added to a dashboard in Gantt view. This is a very necessary reference point for a dashboard.
-
Using both 5 day workweeks and 7 day workweeks in one sheet?
Has anyone had any luck with utilizing both workweeks in one sheet? I have some tasks that need to include weekends, but others that can only be strictly worked on during the workweek. The dependencies remove any logic that I try to apply beforehand.