it would be extremely helpful to be able to increase the font size in the gantt chart view
Dear Community-Members & Smartsheet Development Team, The long-awaited Timeline View feature was recently released. It is a very good feature to use for visual data sharing of timelines (ex. screenshots for presentations). However, we quickly realized in project management that a large number of names are cut off in terms…
Hello Community, I have predecessors and dependencies, but I don't really see a critical, summary or driving path even though I have clicked to show them. Can anyone tell me why? Thanks, Ashley
Now that we can add sub-second durations, please allow a zoom level that can view such durations. I need to visualize processes that are on the order of milliseconds.
Good afternoon, Is it possible through either setting a specific duration or formula to begin a task in the afternoon of a Monday and end at the end of day on Tuesday? I am creating a high-level view of an upcoming store project where some tasks beginning in the PM and finish the following AM and other tasks that start in…
My smartsheet scheduler task will float between two predecessors… meaning it will start at the same time as one task (i.e. 10SS) and finish in coordination with another predecessor (i.e. 12FF). The number of days will technically be variable and change as the predecessors change. Smartsheet does not seem to allow this, but…
This discussion has been merged.
We started with what we thought was going to be a simple sheet that has grown and now had Target Start and Target End date columns. Now we look at is as a Gantt (again not started as a Gantt sheet) So we made parent and child rows, have the settings in Gantt view looking at these date columns. However, if you indent/make a…
Is it possible to add the ability to change the parent row color settings, especially as relates to task bar color in gantt view?