When creating a timeline report to be used on a Dashboard or exported for executive reporting, there is a need to preserve the dependency lines in the Gantt view to assist with understanding impacts of data changes. The Reports functionality does not currently show the dependency lines that are visible on the sheet. It…
Hello, I have created a report of my PP to display Gantt view of tasks and most importantly the dependencies on a dashboard report. However, the Gantt view loses all dependencies when you create a report!! Any solution to this? Thank you!
With a lot of predecessors linking tasks, the gantt view can get crowded and hard to visualize with a lot of additional lines between tasks. I'd like the ability to toggle on/off the predecessor linking arrows. This was a setting in MS Project that I used quite frequently and miss in Smartsheet.
Enhance Smartsheet to automatically adjust predecessors without disconnecting when activity dates differ from baseline dates. Currently, predecessors disconnect when activity dates do not match baseline dates. We require a feature that keeps predecessors connected and adjusts dates to project or forecast new dates based on…
First explaining it slightly, the yellow columns show the sum of the specific cells within the week, currently i do it using range with =SUM(Qty5:Qty10) for the first week. However i wanna make it dynamic such that if i add more rows it wont be a mistake with the sum. For example if i bring up 3 rows from the second week…
Welche gravierenden Vorteile hat die neue Darstellung "Zeitachse" gegenüber der bisherigen Gantt-Ansicht? Ist dies vorrangig eine andere Art der Visualisierung oder gibt es spezielle Funktionen, welche einzig über diese Darstellung ermöglicht werden? Welche Probleme löst diese neue Darstellungsmöglichkeit? Hat jemand…
Once a project is scheduled using predecessors, Smartsheet automatically deleted the predecessors if someone manually changes a start (or finish?) date. Since we are trying to have team members be responsible for updating their tasks, it would be ideal if they could adjust their finish dates directly without the…
Hello! We have baselines set up on our sheet. Is there a way to show the variance visually, in the Gantt or new Timeline view - or is it only visible in that column as a number? Thanks!
It would be nice to have the critical path show when linked to a parent row. I have a parent row (e.g. Testing) where the children (e.g. test 1, test 2, test 3,...) are performed in parallel & have the same finish date, so I often link the successor task(s) to the one parent row vs. each individual test task rows (can be…