In a Gantt with many rows, how to color a date range that spans all rows in a column?
In other words, I have a developed Gantt with many rows. There's an event that I'd like to track in the Gantt that occurs over the course of several weeks. I would like to highlight that date range but not just have it on one row, I want it present on all rows in order to show impact on all activities.
-
Gantt Timescale Settings Global Option
Problem: Our project has stakeholders who use free accounts and utilise the Gantt view. They can’t edit the view settings so it currently opens for them in 2023 (start date of project) and also does not show the year so it can cause confusion and annoyance. Solution: It would be great to have an option, in the Gantt…
-
Gantt
I'm running multiple projects and reporting all in one consolidated Report / Dashboard with Gantt timelines. I'm trying to show one project on one Gantt line, however, break up the bar into different colors for each of the phases within the project. Is this possible, and if yes, how would I set it up?
-
More than one Baseline + Comments
Dear all, To enhance Smartsheet as a comprehensive PM Application, my company and I find that a crucial feature, baseline management, currently needs to be added. While the ability to set baselines is valuable, the limitation of only being able to set one baseline is a constraint. We propose the implementation of a feature…
-
Open to Today's Date when in Gantt view in the Mobile App
When a sheet's Gantt view is set to open today's date it it's settings; the settings do not apply to the Mobile App view. The settings should also take into account when looking at the sheet via the Mobile App.
-
Merged: Option to have baseline start and end dates to individual rows
This discussion has been merged.
-
I would like to see percentage complete on the Gantt view right by the side of the bar in number
I have attached a img as how I want it to can you please guide me on how to
-
%Completion Rollup of projects doesn't make sense for parents of parents
Hello, I'm realizing for a project, the % of completion of the Parent of a Parent task, doesn't consider the size of the Childs of the Parent task. For example, in this case I have two Parent tasks, both of them are 10 days of work, one is 10 task of one day each, and the other is one task of 10 days. Once any of them is…
-
Vertical line in Gantt - Data Date
It would be great if there was a way to add a drop line on the Gantt view i.e a vertical line that communicates important information like the data date i.e the date the schedule was updated These visual tools are important for consultants when trying to communicate data to clients etc
-
Ability to "postpone" a successor task.
If I am working on a schedule for a new equipment installation generally I will have to get a quote, then wait for the quote to arrive, then submit it for Capex approval, then wait for approval, then schedule the installation, then wait for equipment delivery, and then finally installation and commissioning. Preferably I…