Allow editors and viewers to change gantt timescale when printing to PDF
Request: Allow users with editor or viewer access to change the timescale when printing a gantt view to a PDF, and for that setting to be persistent for that user. Background and our use case: I was not aware, but apparently editors cannot change timescale of the gantt when printing to PDF. They can change the display…
-
Parent Row Color Settings: Task Bar in Gantt View
Is it possible to add the ability to change the parent row color settings, especially as relates to task bar color in gantt view?
-
Change "end date" based on status changes
When an end date is used in a dependency setting, you can't use automation or formulas to change it. However, this is when it is critical (pun fully intended)! When someone marks an item as Completed status, it would be helpful if the sheet could update the End Date column to the date it marked completed. For dependencies…
-
Merged: Changing Finish Date based on % Complete Column to Update Schedule for Predecessor Tasks
This discussion has been merged.
-
Simplified Visual Portfolio View
Hello, I am currently using the Project Management Office Template. I have many many projects in here. I am having trouble visualizing the Gannt charts when trying to pull in a lot of projects and compare. I'd like to get something very simple like this: I need to be able to see: How many projects I need to close per month…
-
Duration vs predecessors, for parallel activities (not auto updating on gantt chart)
based in the example below, I have various assignment and activities that run parallel to various construction activities across construction stage. How do i set smart sheet to prioritise predecessor? Research: this behaviour is a known limitation in Smartsheet. Unlike MS Project or Primavera, Smartsheet does not…
-
Gannt chart showing additional days when weekend working
When project settings include for working weekends, why when you give a task a two day duration starting on a Saturday, does it show it spanning 3 days (Sat, Sun, Mon) ? Is there a fix for this please ?
-
Add today line to Gantt Report in Dashboards
The today line should be visible when a report is added to a dashboard in Gantt view. This is a very necessary reference point for a dashboard.
-
Using both 5 day workweeks and 7 day workweeks in one sheet?
Has anyone had any luck with utilizing both workweeks in one sheet? I have some tasks that need to include weekends, but others that can only be strictly worked on during the workweek. The dependencies remove any logic that I try to apply beforehand.
-
ガントビュー PDF出力の際の余白
ガントビューを作成する際に、例えば開始日・終了日を以下に設定して、PDF化した時に、最も古い開始日の前が表示されてしまいます。 2025/9/1~2027/9/30 日付範囲を設定しても、添付のように、設定日より前の日付が表示されてしまいます。 会議資料としての活用も検討しているため、どうにか防ぐ方法はありませんか。 https://us.v-cdn.net/6031209/uploads/VD6L2RF6YJI5/e3-82-b5-e3-83-b3-e3-83-97-e3-83-ab-e3-82-b7-e3-83-bc-e3-83-88.pdf…