-
Displaying multiple time periods in Gantt view
Is there a way to display multiple time periods in Gantt view? Example: you have staff members that are your primary people, and they are contracted for 4 months, and then secondary or "fill" staff members that sit in when the primary is away on sabbatical or similar break. Idea here is that the gantt bar on a given row…
-
Time slots on calander?
We have a machine we want our coworkers to start requesting, daily and hourly. So if Joe wants to use the machine, he could go to the calendar and see an empty time slot between 1pm-2pm and he would be able to block that time out. Does smartsheet have anything like that? Kind of like an outlook calendar
-
Modified SUCCESSORS() function to report more than just direct successors
WHY IS THIS USEFUL? This updated function would allow us to filter the spreadsheet for only the driving path to a particular row#. This would be similar to a filter for critical path, but enable much more flexibility. Current status: I've successfully generated a "Successors" column, listing direct successors of each row,…
-
Allow Gantt view to use Date columns with Column Formulas for Start/End
I'm kind of flabbergasted that this is not currently possible in a Sheet, and I'm struggling to explain to my users why. It is already possible to populate a Date column with a Column Formula and then convert it to a Cell Formula, and then use that column as the Start/End for Gantt view / Project Settings, so the issue is…
-
Time Tracking
I'm new to SmartsSheet and don't see an obvious way to track time, and have it recorded against a task Personally not too fond of % complete - to often I've seen people say/think (legit or not) that they're 90% done, and the last 10% takes as long as the first 90% (or, unfortunately, more) People often think they're almost…
-
Merged: Add elapsed days in predecessor column
This discussion has been merged.
-
Merged: Gantt hour-by-hour
This discussion has been merged.
-
How do add columns in smartsheets dynamically based on a condition ?
I have the date of implementation of the project and I need to dynamically add the columns based on the date. Like for example if I had a 1-2-2024 as my date. It must give ,me 12 months for that date like march 2024 to jan 2025 each column contains 1 month a total of 12 columns and adding to it I have so many projects some…
-
Sharing Report but Not the Source Sheet
I would like to share a report, but not the source sheet. The source sheet has personnel information that I do not want to share with our customer, but I made a report with the information I am comfortable with sharing. However, when I share the report, it is blank because the customer doesn't have access to the source…
-
Gantt Bar with milestone
Would be extremely helpful for high level reporting to be able to have a parent row which is showing the overall Gantt bar be able to display a child row as a milestone marker along that bar. Our project portfolio would benefit from being able to show the go-live milestone that is occurring during the project execution…