Hi, I notice when you add a half day duration to a task, it places the half day at the end of the period, for example a start date of 13/11/17 (Monday) with a duration of 2.5 days will result in the h…
I am just getting started with Smartsheets. So far, I am really liking the ease of set up and functionality. One issue I am struggling with is how to set up intermittent dates for a single task. For e…
Hi everyone, The Smart sheet is very good for short term projects. For a long term project that spans across more than ten years, is there a way to download a entire Gantt chart? Thanks, Liping
How do you change the color of the percentage indicator inside the bar of an individual task? In conditional formatting, you can only change the color of the task bar itself and not the color of the p…
I'm new to this program but not scheduling in general. Is there a way to get each child beneath a parent to calculate % complete automatically, based on the entered start/finish dates and the current …
Hi, Is it possible to show a 'flag / milestone' as well as the duration bar on one line of data. I would like to have a due date associated with a task, as well as a duration. Such that I can see inst…
I'm having trouble having my weeks out calculation work based on the results of a Nested IF Statement. The If Statement works if I use quotation marks around the results which need to display a date. …
i have created a sheet that has a notification date column and then a start date column and then an end date column. i only want the ghant chart to pick up the start and end date columns and not the n…
I have read a few posts regarding the inability of the tool to automatically update duration based on changing % allocation of a resource i.e. Task A will be completed with 1 day duration by Resource …
Hello, I'm needing to create a sheet where a task has a start date of say, 11/1/2017, and then I need to be reminded of something 30 days from the start date, 11/31/2017. Can someone help with the for…