-
Is it possible for summary bars on Gantt to be subject to conditional formatting?
Okay - My conditional formating on this sheet is set to change the color accross the entire row and bar. If status is checked, the gantt bar goes to grey, if not checked, it stays green. The summary bars are not changing. Is this possible? Thanks Jef
-
Individual Days Off
Is there a way that I can schedule individual days off and have them reflected in my Gantt charts? I know the options are available for across the board, but what about individual vacation days. Thanks!
-
Gantt timeline doesn't match project start and end dates
Hello there I am a new user and am stuck! My Gantt chart doesn't seem to update project info from the start and end dates. Also the top bar of the Gantt Chart has irrelevant dates that I cant seem to be able to change. Not sure what I am doing wrong Attaching a screenshot . Many thanks in advance
-
Notify an assignee that the predecessor required to start work has been completed.
I am looking for a solution that will allow an email to be sent to an assignee informing them that their part of a project can begin since a predecessor was completed. Any help would be greatly appreciated.
-
Gantt chart on Mac OS while using Firefox and Safari
Hello, I have the problem that on the trial version its not possible to click in the middle of the sheet and pull the gantt chart wider. Is this a trial thing or is it just not possible to do it on a Mac OS while using Firefox or Safari? Kind regards Arnis
-
Filtering gantt chart
Hello everyone, My goal is to filter a gantt chart so that clients only see a portion of my task list when I export a gantt chart for them. Since I'm brand new to Smartsheet, I'm hoping to run my workflow by all of you to make sure I'm on the right track. I first assemble my master list of project tasks and sub-tasks. The…
-
Gantt view by project days, not dates.
Question, I am trying to create a Gantt chart that tracks a project in terms of days, not dates. For example, Task 1 will run from Day 1 to Day 5, Task 2 from Day 3 to Day 9 (instead of August 3rd- August 8th). Is there a way to do this?
-
Convert gannt chart into monthly revenue forecast
I'm new to Smartsheet and am trying to build a revenue forecast sheet that updates dynamically from an MS Project gannt chart of multiple contract timelines. I'd like to be able import the gannt chart and show the revenue over the gannt chart timeline, have the $ show on the gannt chart by month (or week), then have the…
-
Sight GANTT Issue
I have a report section in a sight including a GANTT chart. The report itself displays the GANNT starting at the first task start date or today with the GANTT paramter. When viewing the sight, the GANNT always seems to start in January. This particular project starts towards end of year so I have 10 months of empty space…
-
Smartsheets for medical practices
Does anyone know if smartsheets solutions can be used to manage medical projects? This would include documenting information that would flow via api into an existing enterprise system.