-
Plotting cost over time
Hi- I am trying to either graphically or with subtotals display cost over time as aggregated preferably by month, but also want to consider by week. I am easily able to plot cost for items that begin or end in a calendar month, but not for items that span months. I am pretty sure each cost would need to be broken down into…
-
Missing columns on XML export of Gantt chart
I have several columns I need to export with my Gantt chart but only the standard Gantt columns seem to export. Every new column I added to the Gantt chart does not export. I even re-loaded the XML back into Smartsheet and the data is missing. Really need this to work to tie into a portfolio management tool the company is…
-
Counting people with the same email domain in a multiselect assigned to cell
Hi there I have a multiselect Assigned To column linked to a contact list. So the contacts are displayed with their full names. Email addresses are shown in the hover over menu for each contact as per usual. I want to count how many of the contacts in the cell belong to the same company. I.e. have the same email domain. In…
-
At Risk Formula Unparseable Error
I am trying to build a nested at risk formula based on the following triggers. -End date is today and Status is not complete it will trigger -There is not enough time between today and the end date for the duration period left. So, if duration minus % complete is 4 days. and the period of time between today and the end…
-
Different font in Gannt header exported to PDF
Anyone else seen this? Not sure if it has been like this since the start or if its a new thing... Is there a setting to correct this?
-
count tasks per week number
Hi community, I'm trying to count the tasks in my gannt per each week in a separate grid. Then i'll make a graph representing work overloads throughout the year. Here is my formula that calculate 0 every time (at least not an error) : =COUNTIF({6530 - Sulfuric project Schedule Range 5}, WEEKNUMBER({6530 - Sulfuric project…
-
Gantt Bar Conditional Formatting not performing as expected
Hello Community, I am attempting to use conditional formatting to change the color of my Gantt bars; however, the conditional format is not being applied to the Gantt bars. Here is my conditional formatting You can see below that I specify a change in row color and Gantt bar color based upon values in booSummaryRow. The…
-
Non-working day shading in Gantt not consistent
When I select Gantt view some of my child tasks have work day and non-work day shading. Non-workdays are light grey and work days are White. This occurs randomly on the sheet. Several child rows have no formatting and some have the grey/white formatting. Why do some have it and others do not. I cannot find a setting for…
-
Changing % complete using a formula in another cell
I know you cannot use a formula in a "% Complete" field. Is there a way to update "% Complete" from a formula in another column (something like a "helper" column)? I have a "Task Status" column with drop down values of Not Started, In Progress, and Complete. I would like to change the value of "% Complete" when I change…
-
Percentage increasing by 100
Hi all, I have an issue where, when inputting a percentage into the %Complete column which accompanies the Gantt, it multiplies this percentage by 100! I.e. it turns 1 into 100% and 100 into 10,000% - screwing with the sheet. The strange thing is, this is only happening for one of my team. When i do it, in the exact same…