-
Elapsed time - 24hr workday - Display bug?
See the attached pic. * The sheet is set for 24hr workdays. Mon-Fri. * There are 2 tasks. one with duration 7d and one with duration e7d. * The e7d task does not display 7 days of working. The gantt chart bar does not show sunday as a working day. * Resource view DOES show sunday as a working day. Bug? Also, the "roll-up"…
-
2 pet peeves - Printing and Filters for columns
Not really a question. More of constructive criticism/asking for better developed features. I use Smartsheet as a scheduling tool at our company, We use master project sheets and a series of project reports and company reports. We generally use Gantt Charts so mostly these comments pertain to that view. For the most part,…
-
Status corresponding to % Complete
I would like to figure a way for the Status Column to auto fill depending on what the % Complete says. For instance: 0% = Not Started 1-99% In Progress 100% - Complete Conditional Formatting is not the way to go and I can't figure out the right If/Then statement to use. New to this world so don't think down on me too much.
-
Highlighting Gantt Chart Date Columns
I have several projects that were suspended due to Covid issues but are starting to open back up. I have to push out everything due to this suspension and I would like to highlight (or just delete/hide) those date columns during the suspension period. Is there anyway to do that? If not, can I submit that as a feature…
-
Planning Calendar conundrums
Hi, Community! I am wondering if anyone else is using SmartSheet for an institutional planning calendar. I chose a template of project with gantt. Most of the tasks on the calendar, however, are annual, bi-annual, semi-annual, etc. I am trying to figure out the best way to handle that. Would I only be able to do it using…
-
Lock Gantt view date on Dashboard from a report
Hello, I am pulling data into a report and displaying on my dashboard. The gantt view always starts on March 15th. Executives viewing the report want to have it start on today's date. The both the source sheet and report's gantt view is checked to start at today's date, but it doesn't translate to the dashboard. I don't…
-
report: take over colors in grid view of a project
Hello, her's my build. I have a project file (file 1) with all details of different project but always with the same structure with different colors. Out of that I created a second PM file (file 2) with links to that main Project file (file 1). --> Until now all fine thanks to the "link from other cell of sheet" this has…
-
Plotting cost over time
Hi- I am trying to either graphically or with subtotals display cost over time as aggregated preferably by month, but also want to consider by week. I am easily able to plot cost for items that begin or end in a calendar month, but not for items that span months. I am pretty sure each cost would need to be broken down into…
-
Missing columns on XML export of Gantt chart
I have several columns I need to export with my Gantt chart but only the standard Gantt columns seem to export. Every new column I added to the Gantt chart does not export. I even re-loaded the XML back into Smartsheet and the data is missing. Really need this to work to tie into a portfolio management tool the company is…
-
Counting people with the same email domain in a multiselect assigned to cell
Hi there I have a multiselect Assigned To column linked to a contact list. So the contacts are displayed with their full names. Email addresses are shown in the hover over menu for each contact as per usual. I want to count how many of the contacts in the cell belong to the same company. I.e. have the same email domain. In…