-
How to import/merge 2 Smartsheet projects plan into 1?
I need to import an existing project plan (call it A) into an already project plan (call it B). A is under a different corporate account than B. I have access to both. I need to merge the 2 project plans into 1. The question probably has been asked but I can't find a "real" answer. Thanks for your help!
-
Dashboard Report Widget: Columns Content and GANTT aren't in the same line
Created a report and added the report via widget to the dashboard. Realized, that the lines are not matching....Content line height is obviously different to the GANTT line height. The report itself looks good and correct - the change is only when presenting in the widget. Is this a 'feature'? Thankful for any help
-
One Dependency for the start, another for the end?
Hi... I'm trying to set up a project that has a task (weekly update reports) that begins with one dependency (e.g., start of project), and ends with another dependency (e.g., on-site work). There are still some administrative tasks that continue after the on-site work is done, but I won't have to continue the update…
-
Build Gantt Chart based on JIRA User Stories Story Points estimations
User story in Jira are estimated in Story Points (0.5, 1, 2, 3, 5, 8, 13, 21...) where each story point can be mapped to ideal days range such as a 0.5 story point = 1d, 1 story point: =2d 2 story points = 3d 3 story points = 5d ... Theoretically it is possible to build a gantt chart of the N user stories as follow User…
-
Color Coding In Progress Tasks within a Specific Time Period in Gantt Chart
Is there a way to color code tasks in a gantt chart that occur during a specific time period? For example, I would like all tasks that are in progress during the months of May, June and July to show as red. I see that I can set conditional formatting to fill the cell background of tasks with specific start and complete…
-
Viewing Deliverable for Multiple Projects by Month - NOT in a Gantt : )
So...any creative ideas for how to achieve something similar to the attached image IN Smartsheet? We want to visual represent high level deliverables across multiple projects for the entire year by Month, however, NOT in a Gantt view and we want it as a 1-pager. Thoughts? Ideas?
-
Does a range of dates fall between another range of dates?
Hello, I have a need to be able to highlight if a range of dates falls between any other range of dates. I have a checkbox column which needs to be ticked if a range of dates conflicts with other range of dates. So for example, we might have a number of projects running throughout the year across different clients and…
-
Baseline/Actual Schedule formula help
Hello all, I'm looking for some help with formulas in my schedule. With the schedule templet, I can insert the dates into the "start" and "finish" columns, the cells will auto populate. I would like to add two additional rows with "Actual Start" and "Actual Finish". When I enter dates into those rows, I'm looking for them…
-
Changing Drop Down Value Based On Current Date?
I am trying to change the drop down value on my Health column based on the current date. Is this possible? ie. If the start date value is in the past, the health column changes to "At Risk" which is one of the drop down choices.
-
Forcing duration and start date to a specific value on Gantt
Dear Community, Is it possible to set a formula so that the Start Date always equals the End Date and that the Duration is always '0'? We are tracking key milestones and are only provided the End Date. I'd like to reduce the manual entry to automatically make the Start Date match the End Date and ensure that the Duration…