-
Customizing Gantt Charts
I am brand new to SmartSheet and my team is primarily interested in finding a Gantt Chart / Timeline maker. I'm hoping the community can help me figure out the following: * Is it possible to make the gantt ribbons flat, without arrows? * Is it possible to show the task name on the ribbons? * Is it possible to make the…
-
Multiple date ranges for one row?
Wondering if it's possible to add more date ranges for a single row, so that multiple occurences of one task will show up in the gantt view. I'm trying to create an advertising schedule for various events, and each ad runs multiple different times during the lead up to each event. I'd rather not create a separate row for…
-
Auto Assign a Predecessor in Gantt
Hi, I have a series of standard processes that have the same dependency and predecessor data each time. I have the primary column as a job number, and then a second column with a drop down list of all the standard processes (I.e. assembly, pre-assembly etc.). If pre-assembly is selected, for example, I always want it to…
-
Gantt Chart Timeline?
Is there a way to have the bars in a Gantt chart to be all on one line? This way the info can be compressed similar to "Timeline View" in MS Project. Can it be done with SmartSheets?
-
Exporting to MS Project with Correct Dates
Hi, I am trying to export a schedule built-in Smartsheet to MS Project to share with a customer. When I export and open the file as an XML, none of the dates are correct. All of the other information appear to be accurate except the Start and Finish Date Thanks, Chris
-
Gannt Export
When I export the gannt chart it is missing the arrows that link predecessors which I can view in my project sheets. Is there a way to get the export to show the same thing? Thanks, Amy
-
Predecessors - Either/Or
Is there a way to make predecessors either/or? For example, I have my task on row 3 tied to tasks on rows 1 and 2. But in my project, both tasks 1 & 2 aren't required, they are an either/or kind of task. So I want my predecessors to be set up that task 3 will start when either task 1 OR 2 have been complete. Is there a way…
-
Adding Task Name to Right Side of Bars
I have an existing sheet that used from a template. It was imported from Project. There are currently no task names beside the bars in the Gantt chart. Is there a way to add the task name to show up to the right of the bars in the Gantt view?
-
Changing Colors of Gant Charts
Is it possible to change the colors of the main timeline bars (not just sub-timelines) on a Project sheet in Gantt view? I do not like the grey.
-
Gantt chart, how to color weekends in OTHER colour than grey?
I have seen some post regarding the possibility of changing the colour of the columns marked as "non working days" and all suggestions to solve this seems to point to the possibility to change the colour of rows. So, I am again asking about the possibility to change the the colour of columns to enhance the readability of…