Is there a way to make predecessors either/or?
For example, I have my task on row 3 tied to tasks on rows 1 and 2. But in my project, both tasks 1 & 2 aren't required, they are an either/or kind of task. So I want my predecessors to be set up that task 3 will start when either task 1 OR 2 have been complete. Is there a way to set them up like this?
