Exporting to MS Project with Correct Dates
Comments
-
Hi Chris,
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? That would make it easier to help. (share too, andree@getdone.se)
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi Chris,
I see that you also submitted a request to our support team about this issue. Could you please confirm whether changing the Auto Schedule feature in Microsoft Project from auto to manual worked, as our support team recommended?
In case it's helpful, I found this resource on the difference between Microsoft Project automatic vs. manual scheduling: https://support.office.com/en-us/article/how-scheduling-works-in-project-5d4f5981-4e9f-4e8e-a699-2ef2a419252f
-
I'm having the same issues as well.
The dates are changed as the XML file is imported to MS Project. You can toggle manual/automatic scheduling once the file is in Project, but it doesn't do anything to change the dates back to what they were in Smartsheet.
-
Hi
i am having the same issues as well. To take the example of Chris - the WBS for ELEC Engineering has no dependencies, yet the dates are changed after importing into MS Project.
File > Export to MS Excel - dates are correct
File > Export to MS Project
- opened in MS Project as new project - dates are wrong
- Now in the same file deleted all lines and keep empty project open
- Open the same XML file and append to existing project - dates are right
MS Project 2013
-
I am finding that smartsheet, when exporting into xml format, is calculating the finish time incorrectly when the duration is in hours. For example, in smartsheet I have a task with no dependencies, a duration of 9h, and a start date of 3/39. In the xml file that smartsheet produces I see this:
<Start>2019-03-29T00:00:00</Start>
<Finish>2019-03-29T08:59:00</Finish>
<Duration>PT9H0M0S</Duration>
Note that the duration is 9 hours 0 mins and 0 sec, but the finish time is 08:59:00.
-
Same here!
Could you please advice what settings are important in Smartsheet in order to make the project export workable with MS Project?Thanks!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives