-
Full Screen View iFrame
Hello... i'm wondering if there's a way to set the default view of a published SMARTSHEET to full screen so that when my team goes to my project webpage and views the embedded SMARTSHEET, it is automatically set to full screen view...? any thoughts ?
-
Date Logic - Weekends versus duration
I'm hoping someone in the community can help me understand the business logic behind the way durations are calculated over weekends in Smartsheet. For context, my sheet has out-of-box settings for working days and hours - Sat and Sun are non-working days, M-F are 8-hour durations. Looking at the attached example, I think…
-
Autofill is working on some formulae in a row and not others
We have been using SmartSheet for about 3 years and have recently developed an approach for our project managers using SmartSheet. We are about to roll it out to our staff but have found an intermittent behaviour that is most troubling. Sometimes, just sometimes, when we insert a new row or add a new row at the end of the…
-
Changing Fiscal Year Start Dates in GANTT Settings
Is it possible to add or change the months listed under "FIscal Year Starts" in the GANTT view settings (timeline display) ? Currently, the default selections are "January, April, July, October." My organization uses an off-standard calendar quarter cycle.
-
Gantt Chart in Dashboards
Hi, I've added a report to my dashboard and used the setting to show the gantt chart. I've set the gantt in the report to open to today's date, but on the dashboard it's not doing that. Is there a way to edit this so the gantt chart opens to today's date in the dashboard? Thanks
-
Resource Allocation and Manipulation
Hi, I am new to Smartsheet and I am trying to create a view for my team where I can see all of the tasks, across multiple sheets (projects), that individual team members are assigned. In other words I want a view where I can see all assigned tasks, with task names, who the tasks are assigned to, dates, and a Gnatt chart if…
-
Showing Milestones in Sights
I use a Sight as a dashboard, so I created a report to pick up only entire schedule for each project. i.e. I have 5 "bars" in the report, represents 5 projects. And I want to show milestones with each bar. Can I do it? If so, how? Each bar is cell-linking so I can go each sheet (project) if I click and see milestones. But…
-
Gantt Chart Milestone separate from Task Duration
Hi, In the Gantt Chart view, is it possible to plug in a milestone date in a task row that is separate from the duration of the task? I see that I can plug in milestones at the end of a specific task, but I am trying to plug in a milestone (to see the little diamond symbol) that is not related to the start/end date of that…
-
Percentage of Total Tasked Complete
Good afternoon everyone! I am trying to format my "% Complete" column to auto populate when changes are made to my "Requirements Total" and "Requirements Complete" (i.e. If I have 10 requirements in my Requirements Total column and I have completed 5 in the requirements complete, which would make my "% Complete" column…
-
Display list of Children
I am looking for a way to simply display a list of children (child tasks). This is identical to Predecessors, where you set the predecessors of a task, however I want to display the list of tasks that follow the current task. Any ideas would be very much appreciated! Mark