Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
PLANNED VERSUS ACTUAL PROGRESS
Comments
-
There is no Baseline feature in Smartsheet as yet. The options are:
Insert KPI's in the form of Milestones and Lock the rows so Editors cannot change them.
Create a copy of the plan when finished Planning and lock all rows, then create a Master project that both the Plan and the Baseline feed into using linked cells.
Create additional Columns for Baseline start and Baseline Finish, Copy Plan dates to these and lock them. Create additional calculated columns to work out the variances.
Not Ideal but all possible.
-
Just jumping on to say I'm looking for this functionality as well! Hope this can be added in the future, would be very helpful.
-
I would love to see this capability as well.
Managing projects is a big part of what I do.
-
Hi Arnold,
I too was looking at SmartSheet feature supporting multiple baseline. Currently, i have do the following. I have 4 columns "Trend Start", "Trend Finish", "Baseline Start" and "Baseline Finish".
The first plan which i review with the team and have it approved, i enter the dates in the "Baseline Start" and "Baseline Finish" columns. At this point, i got to Edit Project Settings and under the "Date rate display", i select "Baseline Start" and "Baseline Finish". This is done to ensure that the predecessor is working properly.
During the project execution, i update the plan (if i see a shift) and start entering the new dates in the "Trend Start" and "Trend Finish" columns. At this point i go to the Edit project settings and change the "Date Rate Display" to "Trend Start" and "Trend Finish". This way, whenever i make any changes in predecessor columns, the "Baseline Start" and "Baseline Finish" dates don't change.
Now at any given time, i can see the drift of the plan.
The only drawback that i see is that one cannot get Gantt graphs showing the plan and the actual/trend.
-
The below article touches on this:
Critical Path - Where Smartsheet fails - Need a Critical Path filter ASAP | Smartsheet Community
-
Hi,
This may help.
Option 1 - 2 plans feeding into report
https://app.smartsheet.com/b/publish?EQBCT=dabaff4f7f114c51a2b30290f2182450
Option 2 - 1 Plan with both Plan and Actuals
https://app.smartsheet.com/b/publish?EQBCT=c024a9c80fff439e89f7014ebbf73c91
Not perfect but both workable.
James
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives