I've been using smartsheets for projects plans for some weeks now and can manage all of the usual functions that I'm used to but I've got a new challenge.
How do i add variable contigency to the duration of a task based on a BRAG status?
Example:
In an Agile development environment the first pass estimate is RED and should contain 20% additional duration to the story points. Second pass (yellow) would be more accurate so +15% duration, etc etc.
Has anyone managed this? I tried a ferw templates but couldnt see this done anywhere