Alpha order or Sheet Order Column List
When working with columns, such as creating a report or Dynamic View, it would be beneficial to have a choice when designing to either add all columns in alpha order or add all columns in the order they appear in the source sheet. Currently, you have to add them one by one and scroll through the alpha list to put them in…
-
ENGAGED 2025 - Creatives and Marketing
Hey there, This will be my second year attending Engaged, and I really appreciated the insights I gained last time. However, as someone in the creative field, I noticed a significant gap in programming tailored to creatives and marketing teams. Last year, the booths, mixers, and breakout sessions were light on content for…
-
ENGAGED 2025 - Creatives and Marketing
Hey there, This will be my second year attending Engaged, and I really appreciated the insights I gained last time. However, as someone in the creative field, I noticed a significant gap in programming tailored to creatives and marketing teams. Last year, the booths, mixers, and breakout sessions were light on content for…
-
How do you standardize addresses in Smartsheet?
Has anyone found a way to validate their address fields in Smartsheet? We are currently using a Smartsheet form to collect business license data and would like to integrate our data to ArcGIS to map the business locations. Currently, we are manually updating all of the citizen-submitted addresses which is a huge time suck.…
-
Increase sheet row and column limits
Hi Guys, What is the possibility to increase the row (20 000) and column capacity? I'm working for a company that headcount surpasses the 20 000 mark which makes it extremely difficult to utilize smartsheets, which we really want to do. This would truly make a huge difference in building a database etc.
-
Merged: If Status is Complete - End Date is Updated to Today's Date - With Dependencies/Predecessors
This discussion has been merged.
-
Using predecessors to dictate duration
Hello, I have a line in a sheet that I would like to start when another line starts and end when a different line ends. For example, I have 4 lines in a sheet: Line A, Line B, Line C, Line D. I want Line A to begin when Line B begins and end when Line D ends. I want the duration to be malleable and change automatically if…
-
Using both 5 day workweeks and 7 day workweeks in one sheet?
Has anyone had any luck with utilizing both workweeks in one sheet? I have some tasks that need to include weekends, but others that can only be strictly worked on during the workweek. The dependencies remove any logic that I try to apply beforehand.
-
Online form
We are looking for a simple Online form that includes the following features: Each question should allow a Yes/No answer There should be an option to attach an image per question The form must be able to work offline (in areas with no signal) It should support sharing responses via email Please see the following YouTube…
-
Coming this quarter! 📢 AI, charts to visualize productivity, and more innovations
Hello Community, This quarter, we’re focused on the Smartsheet Platform for Modern Project and Portfolio Management. Hear from our SVP of Product Management, Ben Canning, and get a peek at a number of innovations coming this quarter that'll make your day to day much easier. Whether or not you’re a project manager by trade,…