-
ADD 3WEEKS, , 2WEEKS, 1WEEK AND 24 HOURS DATE
I need a formula that calculates 3weeks date, 2 weeks date, 1 week date and 24 hours date from a due for each column where the due date is another sheet. Let's say column Citrix status in another sheet is feb/3/22, so under Citrix Status 3weeks from the due date will show in that column and so on I appreciate your help Rob
-
SCC provisioned projects connected and linked, but Summary sheet not showing actual linked cell data
I provisioned a large number of projects and everything seemingly went well. As i start to look around more im finding some oddities. One in particular I don't understand at all... The project provisioned successfully. The data is all there without errors. The summary sheet rollup shows the project with successful (blue)…
-
Help with project metric and resource setup
we are not using Resource Management because it is way too manual of a workflow to manage. Instead I am trying to replicate some level of a resource map by doing the following: there is 4 stage gates that are the primary workload impact for various teams with a specific Start/End for each stage. Team 1 = Stage 1, Stage 2…
-
Changing dependency line colours
Hi, I've previously been able to change a dependency line colour from the default black to any other colour. Now I can't find this feature - has this been removed? Pretty sure it was right click on the dependency line, similar to the right click option on a Gantt bar. Thanks
-
workflow automation - rows aren't moving?
Hello, I created a workflow to move rows once a column status is changed to "complete" within any row. But the workflow didn't trigger, even when I manually changed the status to something else and back again, saved, refreshed, tried again. It finally worked when I moved the row to a different spot in the sheet (shifted up…
-
How to project a completion date with predecessors and durations
I am building out Engineering project plans. I'd like to be able to pre-plan the work out by using predecessors and approximate durations. However, if the first line item in the plan does not yet have an end date the predecessors/duration will not calculate to give a projected end date for the project. I had a call with…
-
Project Server 2016 - Project Health indicator error!
I created the health formula below to address the legend listed below the formula. However, I am getting an error in the formula, can anyone tell me what I am doing wrong and provide some assistance? IIf([% Complete] = 100, "Completed", Switch(([Finish] - Date()) < 75%, "complete within 45 days of finish", ([Finish] -…
-
LookUp and Match a value located in a cell with multiple values and return single and/or multiple va
Hi, I am hoping someone can help with this formula. I was able to get this working using VLOOKUP when there were fewer complexities. In Sheet 2 when there is a value in the "Lot Number" cell, * The formula should look at Sheet 1 to see if the "Lot Number" matches and exists in any of the cells located under the Lot Number…
-
Complex nested IF, AND with traffic light symbols
Hi All, I'm working on automating a symbol highlighter to indicate project progress as well as alerting if key milestones are being compromised. The formula below is structured based on the following columns: * Finish: The Activity completion date * Start: The activity start date * Date: A column containing fixed dates to…
-
Generate Cover Sheet Summary Page off of Data?
We have a spreadsheet listing all of our jobs and I was wondering if anyone knows if we can highlight one of the jobs by selecting it and generating a cover page summary report of just that one job? Any advice would be greatly appreciated! Thanks, Crystal