-
Calculating Number of Items in a Month based on System Generated date field
Hello all - Needing help with a formula to calculate how many requests are submitted via a webform for each month. 2 questions related to this: 1. Can a formula pull just the month from a System Generated cell: Created by (Date)? 2. Where are errors in this formula: =COUNTIF({Date Submitted}, MONTH(@cell) = 1) 'Date…
-
Form conversion
Does anyone know if I can convert the data collected via a form on a tracker sheet to a Project plan? Whilst I appreciate there may be few tasks/mile stones etc. am I able to automate this first initial step? Thanks & any help appreciated
-
IF THEN statement in a symbol column
Fairly new to smartsheet, so not sure if I'm doing something wrong. I have a priority column in my To Do sheet which is a symbol column (High, Medium, Low). I would like to create an IF statement that will automatically change the priority to "Low" once the task is completed (doing this for the purposes of a report I am…
-
Auto Assign a Predecessor in Gantt
Hi, I have a series of standard processes that have the same dependency and predecessor data each time. I have the primary column as a job number, and then a second column with a drop down list of all the standard processes (I.e. assembly, pre-assembly etc.). If pre-assembly is selected, for example, I always want it to…
-
Automate RYGGrey
I need help with a formula to automate my RYGGrey. Here are the rules: If status = complete, grey If status is in progress or not started and finish is in the past, red If status is in progress or not started and finish is today + 5 days (within the next 5 days), yellow If status is in progress or not started and finish is…
-
COUNTIF, ISBLANK, and OR formula
For a particular project category, I'm attempting to count how many times the "Project Status" column is either a blank cell or not "green" (aka complete). These projects will be marked as "Active" on my stats sheet. Here's the formula that I have thus far and I'm receiving an Invalid Operation error: =COUNTIFS({CDVL…
-
Formula to add two columns together that meet the same criteria
Hello, Need some help with a formula, I am trying to add two columns that meet the same criteria from one sheet to total on another sheet. I have tried Sumif and sumifs formulas but they both comeback with errors Here is what I need: On sheet 1 I want to total columnA and columnB on sheet two if they meet (this) criteria.…
-
Hide Errors Until Cell is Populated
I'm calculating the variance between dates using the following formula. The problem is that an error is displayed if the Actual Start Date is not populated as show in the screenshot. Formula used in Variance Start Date: =NETWORKDAYS([Planned Start Date]3, [Actual Start Date]3) - 1 Is it possible to have the Variance Start…
-
Gantt Chart Timeline?
Is there a way to have the bars in a Gantt chart to be all on one line? This way the info can be compressed similar to "Timeline View" in MS Project. Can it be done with SmartSheets?
-
Concatenate two cells
Hi, I need to concatenate data of two cell into one cell. I just use the formula "=[Cell1] + [Cell2])", which worked fine and gave the result "Cell1Cell2", however I need to have space or underscore between values of two cell like, "Cell1_Cell2" or "Cell1 Cell2". My practical requirement is: I need to concatenate "date"…