-
Need Guidance - Can you develop a Generic Project Schedule in Smartsheet
Can you create a generic project schedule in Smartsheet? For example Task 1 starts on Day 1 (start of schedule and month 1) and ends Day 30 (end of month 1), Task 2 starts Day 15 (mid-month 1) and ends Day 90 (end of month 3), Task 3 starts Day 31 (start month 2) and ends Day 180 (end month 6), etc. In Gannt View, you…
-
Sheet Column References in Equations
Is there a way to convert a column reference to a number like you can in excel? My problem is I'm to trying to input an equation that is a simple sum equation referenced to an input cell "x". Whatever number is put in for "x", will add to the column length that sum equation is good for, however when I try to do this, I get…
-
Report Builder - Not Sorting Dates
Hello - I running reports for partners on the team to provide the user a snapshot of tasks due earliest date to latest date. When I sort A to Z on the finish date it is not working. Any ideas
-
Gantt Report for Several Sheets - Can I drag & drop dates in the report?
I would like to be able to drag & drop Gantt dates in my report as we have several projects going concurrently, and the report is great for big picture. How do I do that? Also, how do I reflect a pause in a project, as in we're waiting for info from a client but are working on other jobs in the mean while? I would like it…
-
pallet configurations in smartsheet
Does anyone have a way to figure out pallet configurations in smartsheet given the case specs?
-
Skype for Business - having issues with joining people in conversations
Skype for business has all been set up for us and I can see who is online, however when I try to open up a chat withsomeone it always shows the message, once I have typed in that they cannot join the conversation and they disappear in the window. Is this normal? Is this a Smartsheet thing or an IT department kind of thing?
-
Sorting tasks then go back to original layour
I have several projects i keep on one sheet. I would like to sort them by due date, update items in the most pressing and return to my original nice layout that has all of the projects with headers and then the items to work on under each heading. Whenever I save a change after sorting by due date, I cannot get the…
-
Work week & calendar days on the same sheet
Hi folks - can anyone tell me how I can have a combination of start/end dates that have standard work week durations (Monday thru Friday) as well as efforts that take weekends into consideration (all calendar days)? I know how to make the Gantt dependencies reflect one or the other but cannot figure out how to make 1…
-
Importing to MS Project
Hello all, Can anyone tell me why when importing an exported plan from Smartsheet into MS Project it places some of the %complete to 99% when it should be 0%? It is really annoying. I am currently trying it on a template plan. Thank you in advance.
-
Please make cells wrap and auto size for multiple lines of text.
Currently if I type multiple lines of text in a task description, for example, the cell will not auto format the row's horizontal size. Thanks. -dave