I've noticed that to have the "% complete" column value show up graphically within the Gantt display, the "% complete" column MUST be a free-form entry field. I have another sheet column that uses the "Progress Bar" type. I was hoping to make the "% complete" column calculated based on the value within the "Progress Bar" column (e.g., "Half" would translate to 50% complete, etc.). My developers update the "Progress Bar" column within automated update requests. I was hoping that the calculated "% complete" column could then be used within the Gantt graphical display. However, it seems as if the only way that I can populate the "% complete" column in such a way that it reflects within the graphical gantt display is to enter it manually. Do I have any other options?
Thanks,
Tim