Hello, Can anyone help me write a formula based on the following conditions. Risk Status = "Green" if the following conditions are met: [Delivery Confirmed] is checked Risk Status = "Gray" if the following conditions are met: [Release Date] is Blank Risk Status = "Red" if any of the following conditions are met below:…
Hello, I am trying to add a widget to my dashboard to show the overall Health of a project. I already have a health column in the sheet I will be referencing, and I have added a chart to the dashboard showing the individual tasks and their Health, but I want to add a widget (please see below what I am looking for) based on…
Sorry if this is already in the forum. I searched and did not see it submitted as an idea. It only comes up in other discussions. Issue: When using copy to another sheet, the rows do not maintain their predecessor references. Use Case: We utilize Control Center to provision our projects from a standard "PROJECT TEMPLATE".…
Requesting the ability to use constraint types in a project (Gantt view), similar to the options in MS Project: As Late as Possible As Soon as Possible Finish No Earlier Than Finish No Later Than Must Finish On Must Start On Start No Earlier Than Start No Later Than
Hi all, I have a task tracking sheet, with each task having a start date, an end date, and a duration. I need the end date field to be populated based on the start date and the duration, so I set the dependencies and date range display accordingly on project settings. However, the duration of each task must be calculated…
Hello, is anyone working with a real estate/construction project management template dashboard that they have found helpful? We are a project management firm and we are having trouble finding dashboards that meet our needs.
This discussion has been merged.
I am building a plan with my stakeholders, we have a number of sprint-based tasks that have dependencies. It is very painful to constantly use the 'lag' function for all of these. How can I:1. Link activities using dependencies so they can be visualised in the plan. 2. Allow me to put in a start-date for the successor…
We are an enterprise higher ed group familiar with Smartsheet, but new to using the Google Drive integration. We are (hopefully) transitioning our documentation processes away from clunky word docs into the more automated Google Docs direct from our project register as work requests come through. I've gone through the…