Help Creating a Complex Report
Hi! I am trying to create a report for my ops meeting that will show milestone tasks always grouped under its specific project, followed by non-milestone tasks due. For example: Project Name Starred Milestone tasks Unstarred tasks task 1 task 2 I have all of the above already working, but where I'm getting tripped up is…
-
Control Center Dynamic Reporting NOT ADDING newly created worksheet
I have a blueprint utilizing the Dynamic Report Scope. The newly spun up 'Project Plan' IS NOT being added to the 2 reports I have selected. Why isn't this working? How do I make it work?
-
Anyone having problems with reports not including summary information?
Good Morning, I've been attempting to export a report. The export always comes up without summary information, regardless of the export or send type. Above are screen shots of the report and export. Any help would be greatly appreciated.
-
Merged: Description section for sheets and reports
This discussion has been merged.
-
'Report' where users cannot change parameters/filters/fields
I understand there are Dynamic Views, but it is a little restrictive and limited. is there a way I can share a report with someone but not allow them to change the parameters on the top section (sheets, columns, filters)? without locking down the entire report with "Read-only"
-
Report Printing - Missing Info
I have a report pulling information from 3 sheets. I have results Grouped by the 3 sheets. Why won't the Sheet Name print for the Grouped section?
-
Filter Groups
How to have a filter in a report that shows line items where: - if doc type is one of 8 values AND ASCP is not blank AND if start is in the past AND (% complete is zero OR %complete is blank) OR - if doc type is one of 8 values AND ASCP is not blank AND if finish is in the past AND % complete is less than 1 i've taken a…
-
Ability to Change Your "End Date" in a Smartsheet Report
It would be VERY helpful if we could allow users to change their End Date in a report for a Task. We have 2 Date columns in our project plans. Start Date and End Date. When a user is working off of a Task Report, it would be much simpler if they could change their End Date as to when they completed their task directly…
-
Report Row Ordering:
Hi experts, I'm creating a report that aggregates rows from four Gantt chart sheets, with the goal of displaying each Gantt stacked chronologically, but am seeing some of the rows displayed in the wrong order (see figure). Is there a way to control how rows from different sheets are displayed? Thanks for any assistance!…
-
Project Tracking and Roll up
I'm working on this and is there anyway for the reports i create to not make changes to the existing working smartsheet? I'm afraid I'm going to mess something up on the working smartsheet. As in, if I move columns will it also move on my working smartsheet? How would I change or identify the primary column in a report?…