Hello,
I am working on many project and my boss want me to say which task is finish in advance, in time or late compare to the initial date calculated.
ex:
when the project is finished we want to know which tasks are good and which are wrong.
the task drawing start the 2015 01 01 and must be finish the 2015 01 30
if the real finish date is 2015 01 15 he want to show green 50% time win
if the real time is 2015 01 30 he want to show yellow 0% time win
if the real time is 2015 02 15 he want to show red 50% time late
Someone know how to do that ?