link between the completion percentage and the Resources availability
If I modifty the Percentage of completion to 100% in Smartsheet after the first week of a task that was originally planned for 2 weeks. will it increase the availability of the resources for the second week ? Is there a link between the completion percentage and the Resources availability. Can this be managed ?
Answers
-
Hi @Louis Gaudet —
I don't believe the % completion column will automatically "free up time" for the resource assigned to that row.
However, one way to manage this would be to shorten the duration of the task once it is complete (like from 10d to 5d) or alternatively to move the "end date" date target to the day it was completed.
When you do this, and the task is complete and ended in the past, the resource's availability should open up by that % amount on the next working day.
This does require some manual work, but you could give yourself a signal by using Conditional Formatting to highlight any tasks where complete is "greater than (90%)" or where the end date is within 3 days of today.
Hope this helps.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives