Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Start Date & End Date in Minutes, Hours, and Weeks
Many thanks for the "Duration in Minutes" update. I also wonder if there is a way to enter Start Dates and End Dates in Minutes, Hours, and Weeks; too.
For example; I have a task which starts at the 3rd hour of a workday and no predecessor task to it; but another task before it which ends at the 3rd hour.
Comments
-
The ability to set a specific start and end time was not included in this release but it is something we are tracking feedback for. Thanks for asking!
-
Hi
Do you know if this ability is planned ?
-
Hi,
looking for this functionality also. Especially for team calendars. People often take half days off and it's important to know whether it's morning or afternoon.
Regards - Roland
-
Jean-Francois and Roland, this functionality is something we would like to add to the app in the future but I dont have information on when this might be.
-
Hey Guys, This string outlines exactly what I need as well. After a year, any update? Would be really helpful for us to track submission of task requests by the hour. Thanks!
-
Hello,
There currently isn't a way to track time (hh:mm:ss) in Smartsheet but I've got your vote down for this on our enhancement request list for further consideration.
We appreciate your input!
-
Hi,
we need this feature too, for planing a go-live of a big software-project including a data-migration with many very short tasks (few minutes up to a few hours). At the moment we have to use another tool for this, but we need this feature in smartsheet.
In addition, a more detailed zoom-level would be nice, with the current maximum level all our short tasks are just a thin line on the screen (see attached screenshot).
Regards, Michael
-
I was surprised the Gantt view would not zoom in further than days. So I agree Mike VdK on this need. Not all projects have tasks that are days long.
Also, it seems Smartsheet does properly track dependencies in minutes, but I cannot determine a way to list the start/end TIMES on tasks other than manually entering this data. (See screen shot, I manually put in the time data, but Smartsheet knows from dependencies when to update the day when a task goes past midnight [this project has a 24 hour work day])
Would be nice to be able to show that as it seems to be available "under the covers" of Smartsheet.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 143 Just for fun
- 58 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives