Resource Management and Project plan

I'm trying to wrap my ahead around using RM and how the project plan incorporates into it. Are there templates that work best with RM? I also wanted to know if the change mades in the schedule in RM will appear and reflect on the project plan automatically?

Answers

  • AravindGP
    AravindGP ✭✭✭✭✭✭

    Hi @TPALJA

    To connect a project plan to RM, you will need the following:

    • Dependencies enabled
    • Contact list column where the resource will appear
    • Column to capture allocation percentage
    • Start and End Dates

    There's constant sync now between Smartsheet and RM, so any change you make in Smartsheet will reflect in RM.

    Thanks,

    Aravind GP| Principal Consultant

    Atturra Data & Integration

    M: +61493337445

    E:Aravind.GP@atturra.com

    W: www.atturra.com