Resource Management and Project plan
I'm trying to wrap my ahead around using RM and how the project plan incorporates into it. Are there templates that work best with RM? I also wanted to know if the change mades in the schedule in RM will appear and reflect on the project plan automatically?
Best Answer
-
Hi @TPALJA
To connect a project plan to RM, you will need the following:
- Dependencies enabled
- Contact list column where the resource will appear
- Column to capture allocation percentage
- Start and End Dates
There's constant sync now between Smartsheet and RM, so any change you make in Smartsheet will reflect in RM.
Thanks,
Aravind GP| Principal Consultant
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com
Answers
-
Hi @TPALJA
To connect a project plan to RM, you will need the following:
- Dependencies enabled
- Contact list column where the resource will appear
- Column to capture allocation percentage
- Start and End Dates
There's constant sync now between Smartsheet and RM, so any change you make in Smartsheet will reflect in RM.
Thanks,
Aravind GP| Principal Consultant
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives