Need the ability to filter reports based on project status
Here is what I need.
I have about 50 projects within a workgroup that I am trying to manage.
I have a report of tasks that are due within the next 5 days. Took some cluncky work to differentiate tasks vs summary tasks, but it was easy enough to do.
Next issue / challenge.
When a project stalls for some reason or another, I have no way to exclude that project without hacking a bunch of stuff up.
Recommendations.
Project (sheet) meta-data that is available as a filtering criteria.
WBS Numbering.
Task vs Summary Task (No children == task)
Comments
-
Have you tried using the Reports feature?
http://help.smartsheet.com/customer/en/portal/articles/522214-creating-reports
That would allow you to exclude those projects based on status.
On the summary vs sub tasks, you could create a column checkbox to ID the summary row and just hide it?
Or is there some other criteria that defines the Summary tasks?
We only assign a project # on the Summary Project row and not for the sub task/children so then we can run reports and pull only the tasks with a Project # is not blank.
hope that helps.
tim
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 461 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives