Cell Linking vis-a-vis Predecessor
Dear All,
As mentioned I am trying to cell link the Task and the start date. Post to creating the cell link I add a predecessor to the line,however the link to the Start Date disappears? Could someone please help me with this as this is crucial for me to maintain my Master Plan and Deliverable, dependency tracker.
Many thanks in advance.
Best wishes,
Taru
Comments
-
Hi Taru, I have heard of issues with using dependencies and cell-linking / formulas on date ranges. If you are using dependencies, then your start date would be calculated from the item it is dependent on. Not sure if you can do what you are wanting. Perhaps another community member can confirm.
-
Hi Mike,
Many thanks for your reply.
My issue is that with the dependencies in the row I am unable to cell link the same.
That is the only way i can create a master plan from the sub projects. I am not able to do a report as the senior management wants to see the gnatt chart with the dependencies, hence my dilema..
Let me know if there are any other pointers you can think off.
Many thanks,
Taru
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives