Dates - Gantt Chart
I'm building out a plan with tasks and dependencies and want the dates to populate based off a vlookup. For example, If "Sprint 12" is selected then the proper start date is set in the Sprint Start Date column...which I am doing now with =VLOOKUP([Sprint Start]4, $[Sprint Start]$123:$[Sprint End Date]$136, 3, false). The problem, however, is that date will not populate the Gantt chart since that looks at the project Start Date and End Date columns. I don't want to have to manually set the start and end dates in those columns, I need to set them based off the Sprint number selected. Any help?
Comments
-
Hi Samount,
Can you please give the link of the sheet?
So it helps me to visualize it?
Thanks
Sen -
samount,
If Dependencies are enabled, the dates used for the Gantt chart are Project Settings and can not contain formulas.
My work-arounds typically involve one or more of the following:
- having a second copy of the schedule that does not have Dependencies enabled,
- having second sets of date/duration fields with Reports and/or Filters to see differences and quickly reconcile them.
Craig
-
Here's a read only view - https://app.smartsheet.com/b/publish?EQBCT=16135bedd8274d5287e3799d315fcf24
-
Thank you Craig. That's unfortunate, I suppose I'll just have to work around it as well!
@smartsheets - Would be great to include a feature to override the sheet Settings to point to a different date column. OR, allow the Start Date and End Date columns to be populated with a date from another cell.
Steve
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!