Hello! I am new to smartsheet and am having an issue. We have a schedule where we have several different project type options. Depending on the project type, the project types that are not applicable to that project are filtered out and hidden. So there are several hidden tasks in each of our schedules. The problem I am having is with the % complete column on the parent row. It is calculating the hidden filtered tasks, so it is skewing the % complete for the tasks that are in view. Is there a way to mark those tasks that are hidden as 100%, or not count those tasks in the calculation?
Thank you!