Percentage Complete Calculating Differently on 2 sheets

burkemrich
edited 12/09/19 in Smartsheet Basics

I have a smartsheet that is pushing data to another sheet. Percentages complete are part of the data that is being pushed. On the source smartsheet it shows 45% for a section. On the Target sheet it shows 63% complete for the sames rows. Can anyone explain why I am getting 2 different percentage completes calculated?

12072018_ScreenCap_001.JPG

12072018_ScreenCap_002.JPG

Comments

  • RossL
    RossL ✭✭✭✭✭✭

    If you look at your dates in a Gant view it shows that you have more of the work shown to be done in the second list. the first one the first 3 things on the list only are scheduled to take 5 days where as the ones on the bottom are scheduled to take 10 days.

    I hope this helps.

    end date.PNG

  • Indeed it did. I have gone in and copied over the dure dates and it is not the same on both smartsheet's.

    Thank you!!!