Percentage Complete Calculating Differently on 2 sheets
I have a smartsheet that is pushing data to another sheet. Percentages complete are part of the data that is being pushed. On the source smartsheet it shows 45% for a section. On the Target sheet it shows 63% complete for the sames rows. Can anyone explain why I am getting 2 different percentage completes calculated?
Comments
-
If you look at your dates in a Gant view it shows that you have more of the work shown to be done in the second list. the first one the first 3 things on the list only are scheduled to take 5 days where as the ones on the bottom are scheduled to take 10 days.
I hope this helps.
-
Indeed it did. I have gone in and copied over the dure dates and it is not the same on both smartsheet's.
Thank you!!!
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives