Resource contouring -> variable allocation per day or week on a single task
Hi All,
we often have changing allocations for team members on a given task - ie no a flat 50% allocation for one task across multiple days. For instance - that person's allocation may be 25% the first day 50% the 2nd and third, 100% the 4th and 25% on the last day of the task. This is known as resource contouring in MS project. How has anyone handled in this in smartsheet?
thanks
Comments
-
Hello Andrée,
Smartsheet handles this by splitting out the tasks onto multiple rows. Once the task has been split up, you’ll want to make sure dependencies are enabled on the sheet in order to active the parent roll-up functionality (more on this can be found here: https://help.smartsheet.com/articles/765753-parent-rollup-functionality).
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives