Good afternoon everyone!
I am trying to format my "% Complete" column to auto populate when changes are made to my "Requirements Total" and "Requirements Complete" (i.e. If I have 10 requirements in my Requirements Total column and I have completed 5 in the requirements complete, which would make my "% Complete" column auto populate 50%.
Comments
-
On the face of it, this is quite simple (so I might be missing something ).
Try the formula:
=[Requirements Complete]@row/[Requirements Total]@row
In the % Complete column, format it with the % symbol to show 20% rather than .2
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!